Construction Timeline

Projected Timeline for Construction Related Items
  • Early May 2009 - Soil borings at the site
  • May / June 2009 – Design build contractor prepares pricing
  • Early July 2009 – Proposal due from contractor
  • December 2009 – Review of proposal
  • January 2010 – Construction documents prepared
  • Early March 2010 – Final bid package approved and site work begins
  • Late April 2010 – Foundation construction
  • June / July 2010 – Landscape and parking lot
  • August 2010 – Building enclosed
  • August thru October 2010 – Interior construction
  • October 2010 – Ice goes in
  • November 2010 – Grand Opening