• Update for the week of Sept 13th

Week of Sept 13th

  1. All the masonry is complete
  2. Installing insulation and drywall in the ceiling of the locker rooms
  3. Preparing the parking lot to be paved next week
  4. Working on the remaining vapor barrier installation
  5. Preparing locker room walls for paint
  6. Compressors have been delivered and installed
  7. Tower for condenser has been built
  8. Mechanical room structures are being built