Week of Sept 13th
-
All the masonry is complete
- Installing insulation and drywall in the ceiling of the locker rooms
-
Preparing the parking lot to be paved next week
-
Working on the remaining vapor barrier installation
- Preparing locker room walls for paint
-
Compressors have been delivered and installed
-
Tower for condenser has been built
-
Mechanical room structures are being built
|
|
|
|
|
|
|
|